Completed Works
Location | Scope | Start Date | Completion Date |
---|---|---|---|
Approximately 7kms west of Port Augusta | Construction of a new northbound overtaking lane | Sept 2021 | April 2023 |
Port Augusta to Ceduna | Shoulder sealing | Mar 2021 | April 2022 |
Approximately 7kms west of Port Augusta | Construction of a new southbound overtaking lane | Sept 2021 | April 2022 |
Wirrulla | Construction of a new heavy vehicle rest area | Feb 2022 | 2022 |