The Glenelg tram line is now closed between South Terrace and Moseley Square, Glenelg, until January 2026, with full services resuming for the start of the school year in 2026. This will enable us to fast-tracking construction of the overpasses and reduce impacts on local residents, businesses, road and public transport users.
For substitute bus timetables go to Adelaide Metro tram line closure.
About the project
We're working with the Tram Grade Separation Projects Alliance to:
- make journeys safer and more reliable for everyone
- improve safety for local residents, motorists, pedestrians, cyclists and tram drivers
- provide new, safer and more accessible tram stops with improved pedestrian access
- improve connection and sense of community between the suburbs either side of the tram line
- elevate the Mike Turtur bikeway as a shared use path alongside the tram line
- create new community open space under the overpasses for locals to enjoy.
What's happening
We are removing three level crossings where the Glenelg tram line crosses:
- Marion Road, Plympton
- Cross Road, Plympton
- Morphett Road, Morphettville.
We are also rebuilding the South Road Tram Overpass to accommodate the River Torrens to Darlington (T2D) Project lowered motorway.
Fast facts

Status
Works underway.

Location
Marion Road and Cross Road, Plympton, and Morphett Road, Morphettville and South Road, Glandore.

Jobs created
Supporting 1,115 jobs per year of construction.

Funding
Jointly funded by the Australian and South Australian Governments (50:50).
Subscribe for updates
To stay up to date complete the form on Tram Grade Separation Projects Alliance - get in touch.
Aliance partners
We will deliver these projects with the Tram Grade Separation Projects Alliance.
Along with our Department the alliance includes:
- McConnell Dowell
- CPB Contractors
- Arup
- Mott MacDonald
- sub-Alliance partner Aurecon.