Schedule
Below is a table of the estimated timing of major milestones for the Belair Line Renewal Project.
Activity | Timing |
---|---|
Successful contractor selected | February 2009 |
Contract awarded to John Holland Rail and Coleman Rail to design and construct the Belair Line Renewal | March 2009 |
Start major construction works (Belair line closed) | Sunday, 26 April 2009 |
Complete first stage of track upgrade (Belair Line reopened) | Sunday, 23 August 2009 |