Onkaparinga Valley Road, Nairne Road, and Junction Road intersection upgrade
Fast facts

Status
Open to traffic

Location
Intersection of Onkaparinga Valley Road, Nairne Road, and Junction Road, Balhannah

Funding
Jointly funded (80:20) by the Australian and South Australian governments
About the project
We have constructed a single-lane roundabout at the intersection of Onkaparinga Valley Road, Nairne Road, and Junction Road in Balhannah to increase safety and improve traffic flow.
Improvements made at the intersection included:
a new single-lane roundabout featuring a mountable kerb to facilitate heavy vehicle movements
new pedestrian refuges and access ramps
upgraded lighting
new line marking
new asphalt, kerb and guttering
What's happening
Major construction works on the new single‑lane roundabout at the intersection are now complete.
Some minor finishing works will be completed by end of May 2026 (weather permitting), with speed restrictions in place when required.
We would like to thank the community for their patience and understanding while we completed these important productivity and road safety upgrades.
Timeline
Early works
Site investigations, surveys, service relocations.
Completed July 2025
Construction underway
Major works completed April 2026
Open to traffic
April 2026
Subscribe to project updates
Our privacy statement outlines what information we collect, how we use it and store it.
You can unsubscribe using the link in the email.
Project background
This project is part of the Adelaide Hills Productivity and Road Safety (AHPRS) Package.
The AHPRS includes a range of road improvements to support economic growth, improve road safety and increase fire resilience in the Adelaide Hills area.